$200M LIGHT RAIL EXTENSION GETS UNDER WAY

Written on the 29 April 2016 by Nick Nichols

$200M LIGHT RAIL EXTENSION GETS UNDER WAY

THE second stage of the Gold Coast light rail is off to an immediate start this month after GoldLinQ awarded the $200 million construction contract to CIMIC Group (ASX:CIM).

The company says construction will be due for completion in late 2017, in line with expectations that it will be ready for the Commonwealth Games.

The 7.3km extension will link the city's popular tram network to heavy rail, tracking a route from Gold Coast University Hospital and along Smith Street before heading north along the M1 to Helensvale railway station.

The second stage is seen as critical to meeting the increasing demand for public transport and to support the Gold Coast 2018 Commonwealth Games.

Gold Coast Mayor Tom Tate has already indicated that during his new term of office he will be pushing for the third stage to connect with Coolangatta Airport. The airport revealed this week that it has allocated land for the light rail as part of its 20-year master plan.

The light rail is expected to help meet the Gold Coast's transport needs during the 2018 Commonwealth Games which will attract 6500 athletes and team officials, 16,000 workers and volunteers, and 1.5 million ticketed spectators.

Gold Coast trams will be able to transport up to 3000 people an hour from Helensvale into Southport, Surfers Paradise and Broadbeach.

"The Queensland Government's commitment to delivering stateoftheart public transport has provided us with the opportunity to design and construct this significant light rail infrastructure," says CIMIC Group's CEO Marcelino Fernández Verdes.

"Our capability and major project experience in the rail sector provide the certainty of delivery that is necessary for the expansion of the transport network in one of the fastest growing cities in Australia."

CIMIC' subsidiary CPB Contractors has been awarded the contract, and it has vowed to focus on creating local job and supplier opportunities during the construction phase.

"We continue to work with GoldLinQ to achieve innovative design and costeffective construction solutions for this project, to the benefit of the people of Queensland," says CPB Contractors' managing director Román Garrido.

"In addition, our team will engage with local workers and businesses to develop increased job and work opportunities as the project progresses."


Author: Nick Nichols

Latest News

CROMWELL TRADES STEADILY IN FIRST HALF

CROMWELL Property Group has maintained a steady operating profit at $0.045 per security in the first half of FY17,...

WHY NEXTDC'S STOCK IS SOARING

AFTER posting its interim result, NEXTDC (ASX: NXT) gained more than 12 per cent on the stock market before noon.
...

PWR PROFIT CRASHES AS DOLLAR RISES AND COSTS MOUNT

A RISING Aussie dollar has offset PWR Holdings Limited's (ASX:PWH) overseas growth in the last half, forcing a...

SUPER RETAIL GROUP RESULTS SHINE ACROSS THE BOARD

A WELL-planned and executed half has paid off for Super Retail Group (ASX:SUL) as it posts a net profit result up ...

Related News

EVERYTHING YOU NEED TO KNOW ABOUT THE NATIONAL BROADBAND NETWORK

THE National Broadband Network (NBN) is more than an internet connection, it is an opportunity to transform your b...

WHY EMPLOYEE-OWNED COMPANIES ARE BEATING ASX200 SHARE PRICES

EMPLOYEE-owned companies command a higher share price than their publicly listed peers, reaping a 17 per cent prem...

RISE OF THE MACHINES HAS WORKERS SWEATING

UP TO 3.8 million Australian workers are fearful their job may soon be terminated by a robot, a new survey has shown....

LESS TALK, MORE SMALL BUSINESS ACTION IN 2017

THE future growth and prosperity of Australian SMEs could be undermined if governments lose sight of the sector...

Contact us

Email News Update Sign Up Contact Details
Subscriptions

PO Box 2087
Brisbane QLD 4001

LoginTell a FriendSign Up to Newsletter